New South Wales approved the Deniliquin East battery project on Sept. 24 despite more than 70 public objections. The 100 MW/200 MWh facility is expected to cost AUD 118 million, create 52 construction jobs and two operational jobs, and begin construction in 2027.

New South Wales approved a 100 MW/200 MWh battery near Deniliquin on Sept. 24, granting consent to Bess Arctic’s Deniliquin East project despite more than 70 public objections. The decision clears a major planning step for a facility expected to cost AUD 118 million, with construction scheduled to begin in 2027.

The project is planned about 7 kilometres southeast of Deniliquin, in southern New South Wales. Bess Arctic Pty Ltd lodged the application through Gransolar Development Australia, the Australian arm of Spain-based Gransolar Group. According to the New South Wales Planning Portal, an executive director at the state planning department approved the development on Sept. 24.

The facility is designed to provide 100 MW of power and 200 MWh of storage. It is expected to use about 80 containerized lithium-ion battery modules. The source report says the cells will have 120 MW/240 MWh of total capacity above the project’s nominal rating. The estimated development cost is AUD 118 million, or about US$82.7 million, and the project is expected to operate until 2060.

More than 70 submissions objected, raising concerns that included battery fire hazards, the merits of renewable energy and whether the development fits the area’s land use. Six submissions said consultation had been inadequate. The developer made further project refinements and said it was ready to comply with recommendations from Fire and Rescue NSW.

At a glance
updateWhen: Approved September 24, 2026; constructi…
The developmentA New South Wales planning department executive director granted development consent to Bess Arctic’s Deniliquin East battery project on Sept. 24, following more than 70 objections.

Jobs and Payments for Edward River

The approval allows the project to proceed through planning toward construction, bringing a proposed energy storage facility to a region where objections highlighted safety and land-use concerns. The state assessment identified potential local economic benefits, including 52 construction jobs and two operational positions.

The project is also expected to provide AUD 600,000 in community benefits for the Edward River Council area, which has approximately 9,000 permanent residents. Those figures describe projected benefits in the assessment; the source material does not specify their timing or how the community payment will be administered.

For residents, the decision resolves the development consent question, but it does not make the objections disappear. Fire response arrangements, construction effects and the project’s fit with surrounding land remain matters of local interest as the project advances.

Products Worth Considering

Shark Navigator Lift-Away Upright Vacuum Cleaner, White (NV356E)

Shark Navigator Lift-Away Upright Vacuum Cleaner, White (NV356E)

As an affiliate, we earn on qualifying purchases.

Consultation and the Land Assessment

Gransolar said it followed the New South Wales Undertaking Engagement Guidelines for State Significant Projects. It reported consulting government stakeholders, relevant agencies including Transgrid, and Aboriginal stakeholders, including the Deniliquin Local Aboriginal Land Council.

The company also described engagement with nearby neighbours and the broader community through a newsletter, a survey, notices in local newspapers, pop-up information sessions, a project website and publicly available contact details. These are the developer’s account of its engagement. Six public submissions separately argued that consultation was inadequate.

Planning assessors found the project’s 3.53-hectare footprint would cause a negligible loss of agricultural land in the Edward River local government area. Some objectors were associated with Save Our Surroundings campaign groups, including groups based in Queensland and Victoria. The project site is about 712 kilometres southwest of Sydney.

“The developer said it was ready to comply with Fire and Rescue NSW recommendations.”

— Bess Arctic Pty Ltd and Gransolar Development Australia, as described in the planning material

Fire Measures and Objection Responses

The source material does not detail the final fire-safety design, the specific Fire and Rescue NSW recommendations, or how compliance will be demonstrated. It also does not describe the planning department’s individual responses to the more than 70 objections, or say whether objectors plan further action.

Construction is scheduled for 2027, but no start date or construction timetable is given. The material also does not specify when the AUD 600,000 in community benefits would be delivered or whether the projected employment figures have been independently verified.

Construction Planned for 2027

The next stated milestone is the start of construction, scheduled for 2027. Before and during construction, the developer is expected to address applicable fire recommendations and carry out the project within the approved plans and conditions. The source report does not give a construction start date, commissioning schedule or further approval milestones.

The project is expected to operate through 2060. Further detail on construction timing, safety arrangements and community benefit delivery would clarify how the approved proposal will be put into practice.

Key Questions

What did New South Wales approve?

The state approved development consent for Deniliquin East, a proposed 100 MW/200 MWh battery near Deniliquin in southern New South Wales.

How many objections were submitted?

The project received more than 70 public objections. Concerns included fire risks, renewable energy, land-use compatibility and the adequacy of consultation.

When is construction expected to begin?

Construction is scheduled to begin in 2027. The source material does not provide a specific start date.

What local benefits were identified?

The assessment identified 52 construction jobs, two operational jobs and AUD 600,000 in community benefits for the Edward River Council area, which has about 9,000 permanent residents.

What fire-safety details are confirmed?

The developer said it was ready to comply with Fire and Rescue NSW recommendations. The source material does not list the recommendations or explain the final safety arrangements.

Source: rss

You May Also Like

10 Ways To Make A Small Bathroom Feel Bigger

Discover 10 proven ways to visually and practically expand small bathroom spaces, based on current design trends and expert advice.

Pre-Release Of Polars 2.0

Polars 2.0 pre-release is now available, sparking increased coverage and anticipation among data analysts and developers. Details remain limited.

How to Make Battery Backup More Efficient With Better Device Choices

How to make your battery backup more efficient with better device choices and maximize your runtime—discover the key strategies to optimize your setup.

Insulating A Trussed Cathedral Ceiling

A Rochester homeowner’s ceiling renovation highlights insulation, ventilation and moisture risks in a vented cathedral ceiling with trusses.